DEPARTMENT OF TRANSPORTATION
Federal Highway Administration
[Docket No. FHW-2018-0046]
Executed Memorandum of Understanding Assigning FHWA's
Environmental Review Responsibilities to the State of Arizona Under the
Surface Transportation Project Delivery Program
AGENCY: Federal Highway Administration (FHWA), U.S. Department of
Transportation (DOT).
ACTION: Notice.
-----------------------------------------------------------------------
SUMMARY: This notice announces the execution of the Memorandum of
Understanding (MOU) and approval of the application from the Arizona
Department of Transportation (State) requesting participation in the
Surface Transportation Project Delivery Program (Program). It also
summarizes and responds to the comments received on the draft MOU.
FOR FURTHER INFORMATION CONTACT: Neel Vanikar, Office of Project
Development & Environmental Review, Federal Highway Administration,
U.S. Department of Transportation, 1200 New Jersey Avenue SE,
Washington, DC 20590, (202) 366-2068, neel.vanikar@dot.gov.
David Sett, Office of Chief Counsel, Federal Highway
Administration, U.S. Department of Transportation, 60 Forsyth Street
8M5, Atlanta, GA 30303, (404) 562-3676, david.sett@dot.gov.
Anthony Sarhan, Assistant Division Administrator, Federal Highway
Administration Arizona Division, 4000 N. Central Avenue, Ste. 1500,
Phoenix, AZ 85012-3500, (602) 379-3646, anthony.sarhan@dot.gov.
Steven Olmsted, NEPA Assignment Manager, Arizona Department of
Transportation, Environmental Planning, 1611 West Jackson, Mail Drop
EM02, Phoenix, AZ 85007, (602) 712-6421, solmsted@azdot.gov.
SUPPLEMENTARY INFORMATION:
Electronic Access
An electronic copy of this notice may be downloaded from the
Federal Register's home page at http://www.archives.gov and the
Government Printing Office's database at http://www.access.gpo.gov/nara.
Background
Section 327 of Title 23, United States Code (23 U.S.C. 327), allows
the Secretary of the DOT, to assign, and a State to assume, the
Secretary's National Environmental Policy Act of 1969 (NEPA)
responsibilities and all or part of the Secretary's responsibilities
for environmental review, consultation, or other actions required under
any other Federal environmental law with respect to one or more
Federal-aid highway projects. The FHWA is authorized to act on behalf
of the Secretary with respect to these matters.
The State has submitted application materials requesting to
participate in this Program. The FHWA has reviewed these application
materials, which include public and Agency comments on the application,
and has determined them complete. The FHWA and the State developed a
draft MOU outlining how the State will implement the Program and how
FHWA will oversee the State's implementation as required by 23 U.S.C.
327. The FHWA published a notice in the Federal Register on February
11, 2019, at 84 FR 3275,
[[Page 26504]]
providing the public an opportunity to comment on the preliminary
decision to approve the State's application and public and Agency
comments on the MOU.
The FHWA received 51 comments in response to the Federal Register
Notice. Nine comments were in support of the application and the
State's readiness for this assignment. An additional 42 comments
expressed concern for the State's ability to assume FHWA's
responsibilities for a particular project or generally for the Program.
The comments in opposition mentioned concerns for the State's ability
to manage the environmental review process for the Interstate 11 (I-11)
and Sonoran Corridor Tier II Environmental Impact Statements (EIS).
The FHWA has considered these comments and offers the following
responses. The FHWA notes that by signing the MOU and the State
accepting the jurisdiction of the Federal courts in cases that involve
the compliance, discharge, and enforcement of any responsibility of the
Secretary assumed by the State pursuant to the MOU, the State has taken
on both the responsibility and liability for meeting all environmental
laws under NEPA. Under the Program, the State will make the project-
level decisions in relation to NEPA on highway projects within the
State; however, other Federal agencies will continue to make decisions
respective to their own project-level responsibilities. In the State's
application, the State describes its procedures, manuals, and a Quality
Assurance/Quality Control plan that will guide the State in fulfilling
its NEPA responsibilities under the MOU. Furthermore, FHWA will oversee
the State's compliance with the terms of the MOU through auditing and
monitoring. The FHWA will make the results of all audits available to
the public through notices in the Federal Register.
With the execution of the MOU, the State becomes responsible for
project-level environmental review decisions for projects, including
those not excluded from assignment, for which review began prior to
this date. The FHWA excluded the Tier 1 EIS studies for I-11 and the
Sonoran Corridor from assignment to the State since they are both
nearing completion. However, FHWA assigned the responsibilities for the
Tier-2 EISs for these corridors because the State has the capacity and
ability to complete the EISs without FHWA's involvement in the process.
The FHWA Arizona Division, in consultation with FHWA Headquarters,
has reviewed all the comments received and determined that the State's
application meets all regulatory requirements. Pursuant to the MOU,
FHWA assigns and the State assumes FHWA's environmental review
responsibilities under NEPA, and all or part of FHWA's responsibilities
for environmental review, consultation, or other actions required under
any Federal environmental law with respect to one or more Federal-aid
highway projects within the State. The executed MOU specifies the
assignments and assumptions of NEPA responsibilities and scope of
environmental review, consultation and other activities. This notice in
the Federal Register makes the executed MOU available to the public.
A copy of the proposed MOU may be viewed on the online docket, as
described above, or may be obtained by contacting FHWA or the State at
the addresses provided above.
(Catalog of Federal Domestic Assistance Program Number 20.205,
Highway Planning and Construction. The regulations implementing
Executive Order 12372 regarding intergovernmental consultation on
Federal programs and activities apply to this program.)
Authority: 23 U.S.C. 327; 42 U.S.C. 4331, 4332; 23 CFR 771.101-
139; 23 CFR 773.109; 40 CFR 1507.3; and 49 CFR 1.85.
Nicole R. Nason,
Administrator, Federal Highway Administration.
[FR Doc. 2019-11900 Filed 6-5-19; 8:45 am]
BILLING CODE 4910-22-P