Rescission of Record of Decision and Final Environmental Impact Statement |
|---|
Topics: Interstate Highway System
|
Thomas Nelson, Jr.
Federal Highway Administration
21 June 2018
[Federal Register Volume 83, Number 120 (Thursday, June 21, 2018)]
[Notices]
[Page 28896]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2018-13332]
=======================================================================
-----------------------------------------------------------------------
DEPARTMENT OF TRANSPORTATION
Federal Highway Administration
Rescission of Record of Decision and Final Environmental Impact
Statement
AGENCY: Federal Highway Administration (FHWA), Department of
Transportation.
ACTION: Notice to rescind the Record of Decision (ROD) and the Final
Environmental Impact Statement (FEIS).
-----------------------------------------------------------------------
SUMMARY: The FHWA is issuing this notice to advise the public that we
are rescinding the 2003 Record of Decision (ROD) and the Final
Environmental Impact Statement (FEIS) that proposed to construct a
segment of Interstate 66 (I-66) between eastern Pike County, Kentucky
and western Mingo County, West Virginia.
FOR FURTHER INFORMATION CONTACT: Thomas Nelson, Jr., Division
Administrator, Federal Highway Administration, Kentucky Division, 330
South Broadway Street, Frankfort, Kentucky, 40601, Telephone: (502)
223-6720.
SUPPLEMENTARY INFORMATION: The FHWA, as the lead Federal agency, in
cooperation with the Kentucky Transportation Cabinet (KYTC), is
rescinding the Record of Decision (ROD) and the Final Environmental
Impact Statement (FEIS) for the proposal to construct a segment of
Interstate 66 in Pike County, Kentucky and Mingo County, West Virginia.
The Notice of Intent (NOI) to prepare the Environmental Impact
Statement (EIS) was published in the Federal Register on March 15,
2000. The ROD was issued in October 27, 2003. The FHWA has determined,
in conjunction with the KYTC, that the ROD and the FEIS for the project
shall be rescinded for the following reasons: No foreseeable connection
to the King Coal Highway; significant impacts of the 2003 Selected
Alternative; other regional improvements meet the purposes and needs of
the project; and the lack of funding for the construction of the
project.
Any future Federal-aided action within this corridor will comply
with environmental review requirements of the National Environmental
Policy Act (NEPA) (42 U.S.C. 4321), FHWA environmental regulations (23
CFR 771) and related authorities, as appropriate. Comments and
questions concerning this action should be directed to FHWA at the
address provided above.
Issued on June 15, 2018.
Thomas Nelson, Jr.,
Division Administrator, FHWA Kentucky Division, Frankfort, Kentucky.
[FR Doc. 2018-13332 Filed 6-20-18; 8:45 am]
BILLING CODE 4910-22-P