Major Project Financial Plan Guidance |
|---|
|
Greg G. Nadeau
Federal Highway Administration
December 18, 2014
[Federal Register Volume 79, Number 243 (Thursday, December 18, 2014)]
[Notices]
[Pages 75612-75617]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2014-29653]
-----------------------------------------------------------------------
DEPARTMENT OF TRANSPORTATION
Federal Highway Administration
[FHWA Docket No. FHWA-2013-0042]
Major Project Financial Plan Guidance
AGENCY: Federal Highway Administration (FHWA), Department of
Transportation (DOT).
ACTION: Final Notice.
-----------------------------------------------------------------------
SUMMARY: This final notice announces the availability of Major Project
Financial Plan Guidance. February 2, 2015
DATES: Effective Date: The final notice is effective February 2, 2015.
FOR FURTHER INFORMATION CONTACT: Jim Sinnette, Office of Innovative
Program Delivery, 202-366-1561, james.sinnette@dot.gov or, Janet Myers,
Office of the Chief Counsel, 202-366-2019, janet.myers@dot.gov, Federal
Highway Administration, 1200 New Jersey Ave. SE., Washington, DC 20590-
0001. Office hours for the FHWA are from 8:00 a.m. to 4:30 p.m., e.t.,
Monday through Friday, except Federal holidays.
SUPPLEMENTARY INFORMATION:
Electronic Access
This document may be viewed online through the Federal eRulemaking
portal at: http://www.regulations.gov. Electronic submission and
retrieval help and guidelines are available on the Web site. It is
available 24 hours each day, 365 days this year. Please follow the
instructions. An electronic copy of this document may also be
downloaded from the Office of the Federal Register's Web site at:
http://www.archives.gov/federal-register and the Government Printing
Office's Web site at: http://www.gpo.gov/fdsys.
Background
On September 6, 2013, FHWA published a notice and request for
comments regarding the FHWA's proposal to revise the Major Project
Financial Plan Guidance. Major projects are defined in section 106(h)
of title 23, United States Code (23 U.S.C. 106(h)), as projects
receiving Federal financial assistance with an estimated total cost of
$500 million or other projects as may be identified by the Secretary.
Major projects are typically large, complex projects designed to
address major highway needs and require the investment of significant
financial resources. The preparation of the annual financial plan, as
required by 23 U.S.C. 106(h)(3), ensures that the necessary financial
resources are identified, available, and monitored throughout the life
of the project.
The proposed Major Project Financial Plan Guidance replaces the
existing January 2007 Major Project Financial Plan Guidance. Title 23
U.S.C. 106, as amended by section 1503 of the Moving Ahead for Progress
in the 21st Century Act (MAP-21), allows financial plans to include a
phasing plan when there are insufficient financial resources to
complete the entire project. In addition, 23 U.S.C. 106 now requires
recipients of Federal financial assistance to assess the
appropriateness of a public-private partnership (P3) to deliver the
project. In addition to these MAP-21 changes, the proposed Major
Project Financial Plan Guidance also incorporates a recommendation
included in a 2009 Government Accountability Office report titled
``Federal-Aid Highway: FHWA Has Improved Its Risk Management Approach,
but Needs to Improve Its Oversight of Project Costs'' (GA-090-751). The
report recommended that financial plans include the cost of financing
the project.
Discussion of Comments
I. Summary
All comments received in response to the notice and request for
comments have been considered in adopting this final notice. Comments
were received from the American Association of State Highway and
Transportation Officials (AASHTO), Professional Engineers in California
Government (PECG), Ernst & Young Infrastructure Advisors, LLC (E&Y),
and representatives of seven State DOTs. The following discussion
identifies and summarizes the major comments submitted by the
commenters in response to the September 6, 2013, notice and the FHWA's
responses.
II. General Comments--Approval of Financial Plans
Comment: The AASHTO believes that the FHWA approval of financial
plans for projects with an estimated cost of $500 million or more is
not supported by the language of the statute (23 U.S.C. 106(h)(1)) and
recommends that the guidance be modified to require only that the
project sponsor submit the financial plan to the DOT. The AASHTO notes
that the DOT would still approve financial plans for projects receiving
Transportation Infrastructure Finance and Innovation Act (TIFIA)
assistance. The Nevada Department of Transportation (NDOT) notes that
the statute only requires submission of financial plans and does not
mention approval or concurrence.
FHWA Response: The submission of major project financial plans is
required by statute (23 U.S.C. 106(h)(1)). The FHWA's review and
approval of major project financial plans is to ensure that the plans
contain the information required by 23 U.S.C. 106(h)(3), and is
necessary for FHWA to carry out its stewardship and oversight
responsibilities for major projects. No changes have been made to the
guidance.
Comment: AASHTO recommends adding a statement clarifying that the
guidance does not impose any binding legal requirements.
FHWA Response: FHWA acknowledges that this guidance does not impose
any binding legal requirements. The purpose of this guidance is to
clarify the FHWA review and approval of financial plans. As noted in
the guidance, it applies only to the development and updates of major
project financial plan. It does not apply to the application of any
other Federal requirements. No changes have been made to the guidance.
Comment: The NDOT recommends that the FHWA Division Office
determine the acceptability of the financial plans and respond to the
sponsor within 30 days.
FHWA Response: The guidance states that FHWA will determine a
financial plan's acceptability within 60 days after receipt by the
Office of Innovative Program Delivery Project Delivery Team. Due to the
importance and complexity associated with financial plans and based on
previous experience, FHWA believes that this timeframe is appropriate.
No changes have been made to the guidance.
III. General--Project Exemptions
Comment: The Washington State Department of Transportation (WSDOT)
and the Arkansas State Highway and Transportation Department (AHTD)
recommend that financial plans underway prior to MAP-21 be exempted
from this updated guidance.
FHWA Response: Consistent with this comment the final notice states
that this guidance will be in effect for all financial plans submitted
to FHWA 45 days after date of publication in the Federal Register. This
identifies specific criteria that can be verified by FHWA and provide a
timeline that will allow financial plans submitted prior to the
[[Page 75613]]
effective date in the Federal Register to be reviewed by FHWA using the
previous guidance. This will help ensure a timely and consistent
implementation of the updated guidance. No changes have been made to
the guidance.
IV. General--Other Projects ($100 Million to $500 Million)
Comment: The Alaska Department of Transportation and Public
Facilities (AKDOT & PF), the Minnesota Department of Transportation
(MnDOT), and the PECG recommend that FHWA make a distinction between
the guidance for projects with an estimated cost of $500 million or
more and projects with an estimated cost of $100 million or more that
are not designated major projects. The AASHTO recommends that the
guidance clarify that financial plans for projects with an estimated
cost of $100 million or more that are not designated major projects
will be less detailed.
FHWA Response: The statute (23 U.S.C. 106(i)) uses the same term,
``annual financial plan,'' for both major projects and other projects
(projects with an estimated cost of $100 million or more that are not
designated major projects). The only distinction in the statute is that
financial plans for other projects only need to be made available upon
request, which is reflected in the guidance. Thus, financial plans for
projects $100 million to $500 million must address the same information
as financial plans for major projects. No changes have been made to the
guidance.
Comment: AASHTO recommends that for projects with an estimated cost
of $100 million or more that are not designated major projects, project
sponsors should have the option of submitting a single financial plan
that covers multiple projects in a single geographical area.
FHWA Response: The guidance has been modified to allow project
sponsors to submit a single financial plan that covers multiple
projects with prior concurrence of the FHWA Division Office.
Comment: AASHTO recommends that a project sponsor have the option
of preparing a phased financial plan for a project with an estimated
cost of $100 to $500 million.
FHWA Response: As stated within, this guidance applies to section
106(i) and allows the option to prepare a phased financial plan. (23
U.S.C. 106(h)(1)(B)) No changes have been made to the guidance.
Comment: AASHTO recommends that if a phased financial plan is
prepared for a project with an estimated cost of $100 million to $500
million, that plan should be deemed to satisfy fiscal constraint
requirements for that project.
FHWA Response: The guidance now states that if a phasing plan is
included in an approved financial plan and fiscal constraint
requirements are met for the funded phase, then pursuant to 23 U.S.C.
106(h)(3)(c) the overall project is deemed to meet fiscal constraint
requirements under 23 U.S.C. 134 and 135.
Comment: The MnDOT recommends that the identification of projects
with an estimated cost of less than $500 million, where FHWA requires a
submission of financial plans, be done at the time of the National
Environmental Policy Act (NEPA) decision and include a written
explanation from FHWA.
FHWA Response: The preparation of financial plans for other
projects (projects with an estimated cost of $100 million or more that
are not designated major projects) is required by statute (23 U.S.C.
106(i)). They are to be made available for review upon request by FHWA.
The statue does not require specific notification or rationale for
requesting the submission of financial plans for other projects. The
FHWA Division Offices will work with project sponsors to establish
expectations for financial plans for other projects as part of the
Division Office's overall stewardship and oversight approach. No
changes have been made to the guidance.
Comment: The MnDOT recommends a standardized process be implemented
to ensure that the requirement to submit annual updates based on
reasonable assumptions ``as determined by the Secretary'' is applied
consistently by FHWA.
FHWA Response: This updated guidance along with the technical
assistance provided by FHWA staff to project sponsors is intended to
promote consistency in the FHWA review of financial plans. No changes
have been made to the guidance.
V. General--Project Applicability
Comment: The AHTD recommends that financial plans should only be
completed if the Federal funds used for the project are $80 million or
more.
FHWA Response: The threshold for financial plans is contained in
statute (23 U.S.C. 106(h)(1)) and does not specify a minimum amount of
Federal financial assistance. No changes have been made to the
guidance.
Comment: The PECG commented that the guidance, especially with
respect to the P3 assessment, should not apply to all TIFIA assisted
projects.
FHWA Response: The requirement for the P3 assessment is contained
in the statute (23 U.S.C. 106(h)(3)(D)) and therefore, must be applied
to TIFIA assisted projects that require compliance with major project
financial plan requirements. No changes have been made to the guidance.
VI. General--Guidance References
Comment: The NDOT recommends including, by reference, accompanying
documents that must be read at the same time to understand and put into
context changes in the guidance. The NDOT specifically mentions the
Operational Independence and Non-Concurrent Construction guidelines,
the FHWA Major Project Program Cost Estimating Guidance, and any risk
management reference.
FHWA Response: The reference to the Major Project Program Cost
Estimating Guidance is included in the Major Project Financial Plan
Guidance. This revised guidance replaces the previously separate
Operational Independence and Non-Concurrent Construction guidelines and
there is no FHWA risk management reference included in this guidance.
No changes have been made to the guidance.
VII. General--Fiscal Constraint Requirements (23 U.S.C. 134 and 135)
Comment: AASHTO recommends that project sponsors be allowed to
submit an initial financial plan prior to the completion of NEPA to be
used as the basis for meeting fiscal constraint requirements.
FHWA Response: As noted in the guidance, the FHWA will not approve
a major project financial plan until the selected alternative for the
project has been identified in the NEPA decision document for the
project. An annual financial plan is a comprehensive document that
reflects the project's scope, schedule, cost estimate, and funding
structure to provide reasonable assurance that there will be sufficient
funding available to implement and complete the entire project, or a
fundable phase of the project, as planned. This documentation cannot be
prepared until a project has been identified through the NEPA process.
No changes have been made to the guidance.
Comment: AASHTO recommends that the guidance should state that
financial plans prepared during the NEPA process will have a lower
level of detail than a financial plan that is prepared at a later stage
of project development.
[[Page 75614]]
FHWA Response: This guidance only applies to financial plans needed
to meet the major project requirements. Financial plan approval is
required from FHWA prior to the first Federal construction
authorization. The FHWA will not approve a major project financial plan
until the selected alternative for the project has been identified in
the NEPA decision document for the project. No changes have been made
to the guidance.
VIII. General--Risk Assessments
Comment: The NDOT commented that the guidance does not separate the
Planning Stage Risk Assessment Process with its corresponding level of
effort versus the Major Project Risk Assessment Process. The NDOT
recommends that under the phased plan discussion, additional guidance
should be provided to explain the risk assessment expectations for
projects within the Statewide Transportation Improvement Program
(STIP), for projects 2 to 3 years outside the STIP, and projects within
the 20-year Long Range Plan. The NDOT also recommends that the guidance
describe the specific level of effort for preparing and maintaining a
risk register and include risk management expectations for the projects
and risk strategies to deliver projects early if funding is identified
after the financial plan has been approved.
FHWA Response: This guidance only applies to financial plans needed
to meet the major project requirements. It is not intended to prescribe
to project sponsors the methods and efforts required to conduct project
risk assessments and develop and implement risk strategies. This
comment is outside the established scope of the guidance. No changes
have been made to the guidance.
IX. Project Funding
Comment: For a phased financial plan, the NDOT recommends the
guidance clarify that the identified funded phase is the only portion
of the project that is to be fiscally constrained.
FHWA Response: The guidance does note in Section 4 under Contents
of the Financial Plan that detailed funding information only needs to
be included for each funded phase. No changes have been made to the
guidance.
X. Operationally Independence and Non-Concurrent Construction (OINCC)
Projects
Comment: The AHTD and the Wisconsin Department of Transportation
(WisDOT) recommend that the guidance clarify the definition of OINCC.
Similarly, AASHTO recommends that the guidance clarify that a finding
of OINCC is not required for each phase of the project that is covered
in a phased financial plan. The AASHTO and the WisDOT further recommend
that the term ``phase'' should not be used to refer to a project stage
that is determined to be OINCC. Additionally, AASHTO recommends that
the guidance clarify that a finding of OINCC is required only if the
project defined in the NEPA document will be divided into small
projects, each of which will be covered in a separate financial plan.
FHWA Response: FHWA has revised the definition of OINCC in the
guidance to clarify discussion on phased financial plans. Specifically,
the term ``phase'' will not be used in the definition. The guidance now
specifies that each phase of a phased financial plan does not have to
meet the OINCC criteria and that such a finding is needed only when the
project defined in the NEPA document will be divided into smaller
portions for the purposes of applying major project requirements.
Comment: AASHTO recommends that the application of the OINCC
criteria be flexible and pragmatic. Specifically, AASHTO recommends
that the 5-year and 20-year periods be used as general guides, not
rigid requirements. The AASHTO also recommends that the guidance
include examples to describe the types of projects that would (and
would not) be considered OINCC.
FHWA Response: The FHWA will continue to be flexible and pragmatic
regarding the entire guidance. Due to the varied characteristics of
major projects, examples would not be able to cover the many potential
scenarios and therefore will not be included in the guidance. The FHWA
staff will be available to discuss the OINCC criteria with project
sponsors. No changes have been made to the guidance.
Comment: The Colorado Department of Transportation (CDOT) commented
that the 20-year threshold is excessive because of changing priorities
and the unpredictability of OINCC projects within that period. The CDOT
further recommends that subsequent OINCC projects could be determined
with the remaining criterion of a 5-year threshold between the
completion of one portion and the beginning of the next portion.
Finally, CDOT recommends that if funding is identified for future OINCC
projects, they may be added to a project's financial plan. Similarly,
the AKDOT & PF commented that the 20-year threshold criterion should be
removed and that a State DOT should be able to adapt to changes in
available funding to accelerate the project schedule.
FHWA Response: The OINCC section has been revised to clarify the
application of the criteria and identify when financial plans are
required for OINCC projects. The 20-year threshold ensures that the
OINCC guidance is used for projects that are scheduled to be delivered
over such an extended period of time that it is not realistic to expect
that a project sponsor's financial plan can provide enough detail for
the entire project. The 5-year threshold is the time between the OINCC
project and the next portion of the overall project. The threshold is
used to determine if non-concurrent construction exists between
separate portions of the overall project. Requests for revisions, as a
result of changes in funding availability to an OINCC project
determination, should be submitted to the FHWA Division Office.
Comment: The NDOT recommends that the three criteria for OINCC
should be guidelines, not specific requirements.
FHWA Response: The criteria are considered guidelines and the
application of each criterion will be considered by FHWA on a project
specific basis. No changes have been made to the guidance.
Comment: The NDOT recommends that the guidance clarify when a
financial plan for OINCC projects is required and the level of detail
needed to conduct a risk assessment.
FHWA Response: The guidance has been revised to clarify when
financial plans for OINCC projects are required. This guidance is for
the preparation of major project financial plans. It is not intended to
prescribe to project sponsors the methods and efforts required to
conduct project risk assessments.
XI. TIFIA Projects
Comment: The CDOT recommends that when TIFIA assistance is provided
to a project, an approval from the TIFIA Office for both the initial
major project financial plan and annual updates would simplify and
streamline the approval process for the project sponsors.
FHWA Response: When TIFIA assistance is provided to a project, the
initial financial plan and annual updates are reviewed by both the
Project Delivery Team and the TIFIA Office. A consolidated concurrence
from both the TIFIA Office and Project Delivery Team is prepared. The
Division Office will then provide the approval to the project sponsor.
This review process incorporates a multi-disciplined approach as each
office has a different
[[Page 75615]]
function. No changes have been made to the guidance.
Comment: AASHTO recommends that the guidance clarify that it is
permissible, but not required, to submit a single document that serves
as both the major project financial plan and the TIFIA financial plan.
FHWA Response: The guidance does not require the submission of a
single document, however, it may be more efficient to submit one
financial plan since it is a TIFIA requirement that the TIFIA financial
plan be prepared in accordance with major project financial plan
guidance. The guidance has been clarified.
Comment: AASHTO states that the entity submitting the major project
financial plan may be different than the entity submitting the TIFIA
financial plan.
FHWA Response: FHWA recognizes in the guidance that there may be
multiple documents submitted by multiple project sponsors needed to
meet the requirement of a major project financial plan and the
requirement of a TIFIA financial plan. However, the documents would
supplement each other and together satisfy both requirements. No
changes have been made to the guidance.
Comment: AASHTO states that the requirement to submit annual
updates under a TIFIA loan agreement extends for the duration specified
in the agreement while the requirement to submit annual updates for
major projects extends only through the completion of construction.
FHWA Response: The guidance notes that the submission of annual
updates of projects with TIFIA assistance may extend beyond substantial
completion of the project. The TIFIA office requires its financial
plans to be prepared in accordance with the major project financial
plan guidance after the completion of construction. The guidance also
notes that after the major project requirements have been met,
financial plans with TIFIA assistance may be required throughout the
life of the loan. No changes have been made to the guidance.
Comment: AASHTO recommends clarification that the guidance can be
superseded by provisions in the TIFIA loan agreement or other project
agreements with FHWA and/or DOT.
FHWA Response: All TIFIA loan agreements, regardless of total
project cost, require the borrower to submit annual financial plans in
accordance with this guidance. The methods for developing and updating
major project financial plans presented in the guidance are not legally
binding requirements, and may be modified, as appropriate by TIFIA loan
agreements or other legally binding agreements, to meet both the TIFIA
and other legal requirements. No changes have been made to the
guidance.
XII. Multiple Project Sponsors
Comment: The NDOT asks if a project sponsor, whose only role was to
contribute certain funds to the project, has to provide a certification
for the entire financial plan or just for their contribution.
FHWA Response: The guidance now includes a definition of a project
sponsor. A project sponsor is defined as an entity that provides funds
for the project and administers any Construction or Construction
Engineering/Inspection activities for the project. If an entity was
only providing funds and not administering construction related
activities, then a financial plan letter of certification from that
entity is not required.
Comment: The NDOT recommends defining the term ``otherwise'' in the
sentence: ``If the State DOT granting the concession has also provided
funds (whether Federal-aid or otherwise), then both the public and
private entities would be considered Project Sponsors.'' The NDOT also
recommends adding that P3s should submit a financial plan.
FHWA Response: The phrase ``Federal-aid or otherwise'' has been
replaced with ``any type of funds.'' The guidance states that single or
multiple financial plans can be submitted at the discretion of the
project sponsors. This may include financial plans from P3s.
Comment: AASHTO recommends that the guidance clarify if it is
permissible for each project sponsor to submit a separate financial
plan when there are multiple project sponsors.
FHWA Response: The guidance allows for each project sponsor to
submit separate financial plans for its portion of the project. No
changes have been made to the guidance.
XIII. Financial Plan Submission Process
Comment: E&Y and the NDOT recommend that the guidance clarify that
projects other than design/bid/build projects will not be subject to
stricter standards, but FHWA will allow flexibility in the timing of
the initial financial plan submissions. The E&Y further recommends that
the guidance include examples of possible timeframes and suggest ways
for the FHWA Division Offices to coordinate with project sponsors
regarding financial plan submissions.
FHWA Response: This guidance will be applied to all projects
regardless of procurement method. For all projects, the initial
financial plan should be approved prior to the first authorization of
Federal funds for construction. Since major projects procurement
methods are often unique, there would be too many timeframe examples to
include in the guidance to cover all scenarios. The guidance states
that project sponsors should coordinate with FHWA Division Offices
regarding financial plan submittals for projects other than design/bid/
build. No changes have been made to the guidance.
Comment: The MnDOT recommends that the FHWA Division Office
Financial Manager should be the one designated contact to ensure
conformity across plans.
FHWA Response: The guidance is intended to ensure that consistency
of financial plan reviews. It is at the discretion of each FHWA
Division Office to designate points of contact for its oversight
activities. No changes have been made to the guidance.
Comment: The WSDOT recommends annual updates be submitted no later
than 90 days after the end of each reporting period or ``unless
otherwise specified in other project related obligations (e.g. TIFIA
agreements).''
FHWA Response: The guidance recognizes that TIFIA agreements may
affect submission dates and reporting periods in the Financial Plans
Including TIFIA Assistance section. The revision proposed by WSDOT for
``other project related obligations'' is too broad to be included since
it could be interpreted that non-Federal project related obligations
could impact the timing of annual update submissions. No changes have
been made to the guidance.
Comment: The WSDOT recommends allowing a designee, delegated in
writing from the Chief Executive Officer, to sign the project sponsor
certification.
FHWA Response: It is acceptable for a designee delegated in writing
from the Chief Executive Officer, to sign the project certification.
The guidance has been revised to adopt this recommendation.
XIV: Project Description
Comment: The WSDOT recommends adding examples (e.g. for toll
funding, local government pledged funding, etc.) in the Project
Description of types of anticipated funding. The WSDOT further
recommends providing examples of what should be included when
evaluating the likelihood of anticipated amounts being dedicated.
FHWA Response: The guidance has been revised to remove the
identification of funding in the Project
[[Page 75616]]
Description section of the guidance. The identification of funding for
phased financial plans is discussed in the Project Funds section. Due
to the varied characteristics of major projects, examples would not be
able to cover the many potential scenarios and therefore, will not be
included in the guidance. The FHWA staff will be available to discuss
the different types of projects and project funding sources.
Comment: AASHTO recommends that the guidance not require an
``outline'' of the entire environmental review process. They stated
that it should be sufficient to describe the components of the project
as they are defined in the applicable NEPA document.
FHWA Response: It is important that FHWA has a clear understanding
of the environmental review process since it results in the
identification of the project scope. The term ``outline'' is used in
the guidance to convey that a detailed discussion is not required. No
changes have been made to the guidance.
XV. Project Cost
Comment: The AKDOT & PF and WSDOT recommend that including the
costs of NEPA and other environmental documentation should be
revisited. Large corridor projects often have multiple layers of
environmental documentation that go back over many years. The AKDOT&PF
recommends that FHWA should work with project sponsors to determine
appropriate boundaries for these costs.
FHWA Response: The purpose of including NEPA and other
environmental documentation costs is to have a total cost for the major
project. The FHWA will continue to work with project sponsors to
determine appropriate boundaries for all project costs. No changes have
been made to the guidance.
Comment: The WSDOT, NDOT, and AASHTO recommend that FHWA allow for
alternatives to the FHWA Cost Estimate Review (CER) process, including
those developed by the project sponsor. The WSDOT and AASHTO further
recommend that FHWA not mandate the use of 70th percentile costs.
FHWA Response: The guidance has been revised to address alternative
CER processes or variations from the 70th percentile cost. Alternatives
to the CER process and variations from the 70th percentile cost will be
considered by FHWA on a case-by-case basis.
Comment: The NDOT questioned if CERs are needed for other specific
milestones.
FHWA Response: CERs should be conducted prior to the submission of
the initial financial plan. Major changes that occur in the project
that significantly affect the estimated cost of the project should be
evaluated to determine if an additional CER needs to be conducted. The
guidance has been revised to include a reference to when additional
CERs may be considered.
Comment: AASHTO recommends that the project sponsor participate in
the CER.
FHWA Response: It is important for the project sponsor to
participate in the CER since the project sponsor is often the best
source to provide project information and answer questions. The
guidance has been revised to indicate that the project sponsor should
participate in the entire CER.
XVI. Project Funds
Comment: The CDOT commented that referring to advance construction
funds as State funds will confuse the presentation of the financial
plan. Providing a statement of amounts converted in the annual updates
will achieve the desired objective. The CDOT recommends eliminating
this requirement from the initial financial plan, but instead
recommends reporting the conversion amounts in the annual update. The
WisDOT recommends State DOTs be excluded from reporting annual
conversion amounts when using advance construction to manage funds
internally within a budget year, but not as a special funding technique
that borrows from future Federal funds.
FHWA Reponses: The guidance has been revised to eliminate the
reporting of estimated annual conversion amounts. Project sponsors
should work with FHWA to identify a mutually agreeable method to show
advance construction in the financial plans. In all cases the total
special funding technique amount, the amount converted to date, and the
amount remaining should be reported.
Comment: The WisDOT comments that there would be an inconsistency
between financial plans and State budget authority if the financial
plan included the annual conversion amounts.
FHWA Response: The guidance has been revised to clarify how special
funding techniques are documented and that estimated annual conversion
amounts do not need to be provided. The financial plan will only
reflect actual conversion amounts and so there should be no
inconsistency.
XVII. Financing Issues
Comment: E&Y and WSDOT recommend that financing from debt proceeds
address project-specific debt, or incremental additional borrowing
related to the project, and not programmatic financing. Similarly,
AASHTO recommends that the guidance allow project sponsors discretion
to determine the appropriate level of detail in discussing financing
costs. When a project sponsor is not proposing project-specific
borrowing, AASHTO recommends that the project sponsor should not be
required to quantify borrowing costs. Where a project sponsor is
proposing to issue bonds specifically for the project, AASHTO
recommends that it should be sufficient for the financial plan to
provide an estimate of annual payments and revenues.
FHWA Response: FHWA recognizes that project-specific financing cost
information is more readily available. When project-specific debt is
issued, the financial plan should show the total cost of financing for
the project, which could be an estimate if that is the best information
available at the time of the financial plan submission. The
programmatic financing cost discussion would be at a programmatic level
of detail. No changes have been made to the guidance.
Comment: The AKDOT&PF and WSDOT believe that the adequacy of the
financial plan should be based on the ability to fully fund and
complete construction, not on future debt service for non-Federal
financing. The WisDOT recommends flexibility to allow project sponsors
to determine the level of total debt financing for a project because at
the time of the initial financial plan adoption, the total financing
cost for a project is not known.
FHWA Response: The purpose of the Financing Issues section of the
financial plan is to document financing costs and estimates to fully
fund and complete construction of the project. Non-Federal financing
will not be evaluated and FHWA will not make a determination on whether
the project sponsor is capable of repayment. Any changes to the amount
of financing costs or estimates can be reflected in annual updates to
the initial financial plan. No changes have been made to the guidance.
XVIII. Cash Flow
Comment: E&Y and the NDOT recommend adding clarification or an
example narrative for the discussion of the project sponsor's ability
to deliver its capital program in the guidance. The
[[Page 75617]]
MnDOT and NDOT offer that the project sponsor could be allowed to refer
to a current annual STIP Financial Report to demonstrate the project
sponsor's ability to deliver its capital program.
FHWA Response: The guidance has been revised to remove the
discussion on the overall impact of the project sponsor's ability to
deliver the State transportation capital program. As discussed in the
guidance, the review of the STIP is an important step by FHWA in the
review and approval process for financial plans. This review of the
STIP, along with the option of submitting a phased financial plan,
makes further discussion on the overall impact of the project sponsor's
ability to deliver its capital program unnecessary.
Comment: The MnDOT recommends that FHWA consider drawing on the
expertise of financial credit rating agencies when assessing the
credibility of a project sponsor for major projects.
FHWA Response: This guidance is not intended to document the FHWA
methods and efforts required to assess the creditability of a project
sponsor. This comment is outside the established scope of the guidance.
No changes have been made to the guidance.
XIX. Public-Private Partnership Assessment
Comment: The PECG recommends that the P3 assessment include a
complete cost-benefit analysis to deliver the project with a detailed
list of contents in the analysis.
FHWA Response: Title 23 U.S.C. 106(h) requires the financial plan
to include an assessment regarding the appropriateness of a P3 to
deliver the project. The guidance includes appropriate discussion
regarding the comparison of benefits and challenges of procuring the
project as a P3 compared to traditional procurement methods. The
guidance is intended to allow different assessment methods by project
sponsors. No changes have been made to the guidance.
Comment: The PECG recommends that public servants be used, rather
than private sector employees, to perform all construction inspection
functions for P3 projects.
FHWA Response: This guidance is for the preparation of financial
plans and is not intended to prescribe project sponsor decisions for
how the project is managed, including how project inspection services
will be performed. This comment is outside the established scope of the
guidance. No changes have been made to the guidance.
Comment: E&Y and the NDOT recommend that FHWA should not second
guess the project sponsor's delivery decision based on the P3
assessment.
FHWA Response: The purpose of the P3 assessment is to provide a
brief documentation of the procurement decisionmaking process. The P3
assessment is not intended to prescribe a process for the project
sponsor's delivery decision or to evaluate the decision of the project
sponsor. The guidance is consistent with this purpose. No changes have
been made to the guidance.
Comment: The AHTD recommends that if P3 mechanisms are not allowed
by State law, there should be no reporting requirements. The WisDOT
recommends that if there is no enabling legislation for P3s, then a
generic statement to that effect will suffice for responding to this
section. The AASHTO recommends that the consideration of a P3 be brief
if it is obvious that a P3 is not viable because of State law and there
is no reasonable basis for expecting that law to change.
FHWA Response: The guidance identifies the items that should be
covered in the narrative to assess the appropriateness of a P3 to
deliver the project. The absence of legislative authority is included
in these items. Therefore, if State law does not allow the use of P3s,
then the narrative should reflect that. No changes have been made to
the guidance.
Comment: The AHTD recommends that when tolling, bonding, or TIFIA
financing methods are not appropriate for the project, previous
analyses should be adequate with no further reporting requirements.
FHWA Response: The guidance notes that the P3 assessment is a
narrative describing the process used to consider whether a P3
procurement is appropriate to deliver the project. Referencing and
summarizing previous analyses may be adequate to meet these criteria.
No changes have been made to the guidance.
Comment: The MnDOT states that the analysis for a P3 delivery would
be based on historic rather than recent consideration. The WSDOT
recommends that only the results of earlier P3 analyses, if any, should
be identified in the initial financial plan. Similarly, AASHTO
recommends that the guidance should specify that the discussion of a P3
should include the reasons for or against using a P3 when the decision
is made by the time the initial financial plan is submitted.
FHWA Response: A P3 assessment can be based on a previous project
level analysis. If a P3 assessment has not been conducted at the time
of the initial financial plan preparation, then an assessment must be
done before the initial financial plan is submitted to meet the
statutory requirements in 23 U.S.C. 106(h). The guidance has been
revised to clarify when a P3 assessment is required for phased
financial plans. The P3 assessment for the unfunded portion of a phased
financial plan should be provided in annual updates as the portion of
the project is added to the financial plan.
Comment: AASHTO recommends that annual updates to a financial plan
should not be required to revisit the appropriateness of a P3, and that
it should be sufficient for the annual updates to summarize the
assessment that was included in the initial financial plan.
FHWA Response: There is no need to revisit the appropriateness of a
P3 in the financial plan, except in the case of phased financial plans
when a new portion of the project is added or when the procurement
method changes to use a P3 or not. No changes have been made to the
guidance.
XX. Final Major Project Financial Plan Guidance
The FHWA has updated its Major Project Financial Plan Guidance. The
FHWA published the proposed guidance for public comment on September 6,
2013. After considering all the comments, the FHWA has incorporated all
appropriate edits into the guidance. As such, the revised guidance,
which can be found at http://www.fhwa.dot.gov/ipd, will be in effect
for all financial plans submitted to FHWA February 2, 2015.
Authority: 23 U.S.C. 315; 23 CFR 633.104(a)
Issued On: December 9, 2014.
Greg G. Nadeau,
Acting Administrator, Federal Highway Administration.
[FR Doc. 2014-29653 Filed 12-17-14; 8:45 am]
BILLING CODE 4910-22-P